W. Rolston Road Reconstruction Project - Update Five June 23, 2025
The contractor has completed the underdrain and stone base on the north side of W. Rolston Road from N. Bridge Street to just west of Beach Buggy Lane. They are now moving operations back to the east to complete the south side of the road from just west of the car wash westward back toward Beach Buggy Lane. This section of work will provide intermittent access to N. Bridge Street by means of one lane, and ongoing access to the detour on Hogan Road. Motorists may have temporary delays through the construction zone as trucks are loaded in the open lane. When the open lane is clear, motorists can proceed with caution.
Work zones require extra caution, and we ask for your support in keeping safety a top priority. Please remember to:
· Slow down and stay alert when approaching and traveling through construction areas.
· Follow posted signs and directions from workers.
· Plan ahead for potential delays and seek alternative routes when necessary.
We appreciate your patience and cooperation as we work to improve W. Rolston Road.
Working together we can create a safer and more efficient roadway while minimizing disruptions.
If you have any additional questions or concerns, please reach out- 810-735-7980
Don Grice
Director of Public Works