Lindenwood Neighborhood Improvement Project - Update Seventeen
The asphalt contractor will be returning to the project tomorrow to address some asphalt quality issues that have been identified throughout the project. This work will be focused on several small areas, so there should be minimal travel disruptions. We anticipate that one lane of travel will remain open in the work areas. Despite the open lane, we recommend motorists avoid the work zone if possible. This work should be completed within a couple of days.
We are also receiving a lot of calls regarding landscape repairs, or the lack thereof. The contractor will continue to move through the neighborhood until all landscape repairs have been completed. If you believe the landscapers have completed your street, but not your property, contact us so that we can make sure you haven’t been overlooked.
If you have any concerns specific to your address, please contact the city to make sure your concerns are scheduled to be addressed.